FedEx Ground King of Prussia, PA

Project Details

CMS successfully complete 3,330+ LF of footing and foundations for a FedEx Ground distribution center in King of Prussia, PA.

The grueling 10 week schedule was fast paced and achieved through the highest levels of leadership, planning and execution. Constant design changes and input from the other crafts meant communication was paramount for success.

Utilizing a combination of gang and handset forms, daily manpower was upwards of 30 team members to get the job done.

CMS self-performed excavation, backfill, forming and pouring of the concrete.

Tools & Equipment

• 35k # excavator
• 10k # lull
• Mevalite forms

Completion Date

2016